Execution of polyethylene and steel gas supply projects through the supply of goods, equipment, and installation (PC) in gas supply areas 1 and 4 in Shiraz and its suburbs
    
View : 127
    

Execution of 22,004 meters of gas supply project at 60 PSI pressure

Steel pipeline installation (2 to 10 inches, 2,004 meters)

Polyethylene pipeline installation (63 to 160 mm, 20,000 meters)

 

  • 607 steel pipe welds
  • 2,004 meters of pipe cleaning, priming, and insulation
  • 22,300 meters of trench excavation in non-rocky terrain

The project was completed in 360 days.