Execution of polyethylene and steel gas supply projects through the supply of goods, equipment, and installation (PC) in gas supply areas 1 and 4 in Shiraz and its suburbs
6/10/2025 9:05:45 AM
View : 127
Execution of 22,004 meters of gas supply project at 60 PSI pressure
Steel pipeline installation (2 to 10 inches, 2,004 meters)
Polyethylene pipeline installation (63 to 160 mm, 20,000 meters)
- 607 steel pipe welds
- 2,004 meters of pipe cleaning, priming, and insulation
- 22,300 meters of trench excavation in non-rocky terrain
The project was completed in 360 days.
Contact With Us